Now it so far: On 9 March 2011, so is Ash Wednesday, start of work on the redesign of the Konrad-Adenauer-Strasse, phase II. The section extends from the new roundabout to the Bailiwick of road or up to the Martin-Heyden-Strasse.

Work can hasten away in four phases: Phase 1

(March to early April): The Construction
Dohmen starts with setting up the site and sets up the vast detour routes. Immediately afterwards, the two channels between the roundabout and the entrance hall, including the provision of land connecting cables manufactured or renewed. The entrance to City Hall, meanwhile, is only on the road coming Sittarder possible.




After completion of the channels between the roundabout and the entrance hall of the channel in the City Hall entrance on a 15 m long section updated.



The entrance to City Hall and the parking needs at this step of the Martin-Heyden-street on the sidewalk along the kindergarten place a traffic light control.
Phase 1 lasts until around the end of the 14th Week (April 9).

Phase 2 (April and May):
It is the renewal the channels with the property connection lines from the Town Hall driveway towards Heinsberg road junction. During the canal construction, this section started with the road between the roundabout and the entrance hall. The entrance to the town hall takes place during the still from the Martin-Heyden-Strasse.
Phase 2 lasts until around the end of the 20th Week (May 21).



Phase 3 (late May to mid June):

completion of the canal from the Heinsberg Road to the Bailiwick Road. To enable the access to the hospital, is the reverse of the one-way direction in the Heinsberg Road made. From the completion of road between the roundabout and the entrance hall is the entrance to City Hall back from the roundabout.
Phase 3 lasts until around the end of the 24th Week (June 18).




Phase 4 (late June to mid October): completion of road construction between the City Hall entrance and the Bailiwick of road, or the Heinsberg Road.
Phase 4 continues until around the end of the 41th Calendar week (October 15).

Gymnasium St. Ursula and the weekly market are from the roundabout to be reachable. At the weekly market days off the square in front of the parish church of St. Mary's to Parking for cars released.

The accessibility of all entrances, especially the supply of retail stores will be possible at any time.